Meeting to discuss new sidewalk on West Broadway scheduled for July 14
Ryan Shiner
COLUMBIA, Mo. (KMIZ)
An “interested parties” meeting has been scheduled to discuss adding a sidewalk in a portion of West Broadway, according to a Monday press release from the city.
The meeting is scheduled for 5:30-6:30 p.m. Monday, July 14 at the Activity and Recreational Center at 1701 W. Ash St.
Organizers will discuss a concept for a sidewalk to be placed on the south side of West Broadway between Maplewood Drive and West Boulevard, the release says. The project is expected to include a 5-foot-wide sidewalk with a 3-foot-wide grass parkway and will include reconstructing driveway approaches, the release says.
west_broadway_sidewalk_preliminary_planDownload
If the project is approved, construction would start in the spring of 2027, the release says.
The public can leave comments on the project’s BeHeard site.