UM Board of Curators approves $80 million transmission line project, $15 million McDavid Hall renovation
COLUMBIA, Mo. (KMIZ)
The University of Missouri System Board of Curators unanimously approved a pair of high-dollar projects during its meeting on Thursday.
An $80 million substation and transmission line project and a $15 million residence hall renovation project were approved under the consent agenda.
Meeting documents show the contract for the transmission line project was approved for LUZCO Technologies LLC out of St. Louis. The project will build a new electrical substation and two overhead 69-kilovolt transmission lines “connecting Mizzou’s campus to the regional electric grid.”
The substation will be located south of Stadium Boulevard and east of Champions Drive in Columbia, documents say. It will replace the existing Stadium Boulevard Substation at the southeast corner of Monk Drive and Hospital Drive, documents say. Curators previously approved a $49 million project to replace that substation in another location, but “due to cost accelerations and high demand for electric components, bids substantially exceeded the approved budget,” meeting documents say.
This comes after the Columbia City Council agreed to move forward with a $35 million 161-kilovolt transmission line project during a contentious meeting on Monday night that saw pushback from several residents.
Meeting documents for the Board of Curators says the University of Missouri’s Columbia campus needs about 50 megawatts of electricity, which is supplied through the MU Power Plant and Midcontinent Independent System Operator regional grid. The Power Plant has a maximum generating capacity of 54 megawatts, documents say.
Documents claim MU’s campus “is projected to exceed the Power Plant’s maximum generating capacity by 2030.” It’s expected to be completed by April 2029.
McDavid Hall renovationsThe Board also approved a $15 million renovation project for McDavid Hall, which is located at Elm and Sixth streets near Peace Park.
Helix Architecture and Design was approved for the project.
“As MU Housing advances its long-term strategy, conversion of this facility to academic use aligns with the MU Master Plan and evolving student preferences for housing. This project advances the University’s commitment to improved space utilization by relocating the Department of Psychological Sciences from McAlester Hall to a setting that better supports its academic, research, and student needs,” meeting documents say.
Todd Graves named Board chair againThe Board also picked Todd Graves to serve as chair and Robert Blitz to be the vice chair again. Their next terms begin Jan. 1.
“It’s an incredible privilege to continue serving as chair, and I am grateful for the confidence placed in me by my fellow board members,” Graves said in a statement. “This year’s historic momentum shows our success on the world stage and the power of our shared vision across the four UM institutions. Together with President Choi and university leaders, the board and I look forward to advancing transformational initiatives that progress our mission of service and positively impact all Missourians.”
Click here to follow the original article.