Cañon City planning less impactful street projects for 2027 than in previous years

Scott Harrison

CAÑON CITY, Colo. (KRDO) — The past three years brought major street projects to town, but next year should be a little easier for residents and traffic in one south side neighborhood.

In January, crews begin a project to replace an aging water main under five blocks of Griffin Avenue, between 4th and 9th streets.

Leo Evans, the town’s public works director, said that the project — which won’t end until fall — will include stormwater upgrades, building sidewalks on the north side of the street, and rebuilding and paving the street.

Preliminary work has already begun, with crews from Atmos Energy relocating natural gas lines.

The state is financing the water main, which covers 20% of the project’s overall cost.

Evans said that the main is a century old, and officials want to replace it before it becomes a more expensive issue.

For residents who want to learn more about the project and ask questions, the city is hosting an open house from 4:30 p.m. to 6 p.m. Thursday evening at the Lincoln School of Science and Technology, 420 Myrtle Avenue.

“One of my concerns is — as property owners in this area — will we still have off-street parking when it’s done? asked neighbor Dave Schmidt. “Where are they going to end it at? That could be a debate. It’s something I’m genuinely interested in.”

Regarding standard street repaving projects, College Avenue tops the list; it stretches in front of the high school, between 3rd and 15th streets, on the north side of town.

A series of more impactful projects began in 2024, when the town finished installing pedestrian signals and crosswalks along US 50, just south of downtown; in 2025, crews completed a major beautification project on the east end of Main Street downtown.

Both of those projects were largely funded by the Colorado Department of Transportation (CDOT).

Last month, the town finished a year of construction in two separate projects along two miles of 9th Street, north of downtown; it involved rebuilding one segment, replacing a water main in another stretch, repaving and concrete improvements.

Much of that work was funded by the town’s 2A intitiative — a 1% sales tax increase passed by voters in 2016 and extended a year ago for anothger ten years.

This winter, crews will make their fourth try at relocating a natural gas line under railroad tracks at the east end of Main Street; previous attempts ended with a broken pipe and a damaged water main.

The delay has held up a stormwater project planned for the area.